Rangiuru Business Park

Civil EngineeringSurveyingTraffic & transportationDevelopment AdvisoryDesign StudioThree WatersLand DevelopmentPlanning

Rangiuru Business Park is a project close to our hearts here at HG.

Bringing together most of our disciplines including planning, civil engineering, three waters and surveying, we’re thrilled to see Quayside Properties’ vision come to life to build a thriving and connected business park for the Bay of Plenty region.

Beginning in 2006 leading a plan change to rezone 148ha of rural land to the east of Te Puke, following the approval of the plan change and subsequent variation, HG has obtained numerous resource consents including stormwater discharge, bulk earthworks, water takes and subdivision to enable development within the park.

Project Lead and HG Technical Director, Grant Rae, says he and the team are so proud to be a part of the project which is a flagship project for the region.

‘’The transformation of the park is huge. If you’re driving along the Tauranga eastern motorway, you’ll see a hive of activity with contractors working on multiple contracts,’’ says Grant.

‘’We’re all working together to create the roading, wastewater, water supply and stormwater infrastructure required to bring the park to life’’.

Following detailed stormwater and flood risk modelling by our three waters team, a 50-ha stormwater pond and wetland sits to the north of the site. That’s the equivalent of 48 rugby fields!

Grant says the pond will provide important ecological and environmental outcomes for the surrounding areas as well as mitigate any flood risk within the business park and downstream.

‘’It’s so satisfying to see the park come to life. As professional consultants, this is what thrills us. We get to see a community flourish and our planning come to fruition,’’ says Grant.

Our services

General consultancy:

  • Lead consultant for the development of Stages 1 and 2

  • Overall delivery of consenting, design and survey work

  • Co-ordination and liaison with all partner organisations and other third parties

Infrastructure:

  • Consenting, detailed design, approvals and construction observations of major infrastructure projects including two wastewater pump stations, 6.5km of wastewater rising main, water reservoirs and pump house, 50ha stormwater wetland

  • Consenting, detailed design and construction observations of all bulk earthworks across Stages 1 and 2 and stormwater wetland

Stormwater modelling:

  • Extensive stormwater planning, modelling and design work in a complex stormwater environment

  • Hydrodynamic flood modelling of entire downstream section of the Kaituna River flood plan

  • Natural hazard assessment and reporting for flooding from heavy rainfall

  • Detailed design of a 50ha stormwater wetland

  • Preparation of Stormwater Management Plan and Operations and Maintenance Plan for the park and wetland

  • Detailed design of pipe and swale networks throughout the business park to convey stormwater

Planning and survey:

  • Earthworks consents

  • Water take consents

  • Subdivision consents and scheme plans

  • Range of minor land use consents

  • General consenting advice

  • Full land transfer and s223/s224 processes

Construction:

  • Preparation of a range of NZS3910 and NZS3916 construction contracts

  • Co-ordinate tender process and involved with tender evaluation, assessment and negotiations

  • Full suite of MSQA services across a range of infrastructure, subdivision and civil contracts to the value of $60million (to date)